
Kindercare Prior Lake
Project Overview
Construction Duration: 214 days
- Mobilization: 04/15/2019
- Substantial Completion: 11/15/2019
Size: 10,782 Square Feet
The Prior Lake KinderCare was completed within seven months of mobilization. With nine separate rooms for infant through Pre-K, a gym, and two separate playgrounds for the different age groups this KinderCare has a capacity for 144 children. This space also houses a private kitchen, dry storage, laundry facilities, director office, and staff lounge.