Metro Office Update
May 31, 2022
We’ve seen some big progress for our new metro office! This past week we completed soil corrections, dug, formatted, and poured footings, and also ran drain pipe out of the elevator pit footing. We established drain locations coming out of the building and prepared for sleeves that are arriving this week. With an inspector present, we turned the water on for the first time and also finalized our budged for the interior buildout.
Over the next few weeks we will continue to form and pour the footings and foundation walls, install underground plumbing, electrical and storm structures, and hook up Temp Electric. We continue to move forward with this project and if you are interested in keeping up with this project’s progress, make sure you check back for our monthly updates which will be posted around the first of every month!